An apartment building goes up in a fixed order. The ground is secured, the crane goes in, the basement is dug and poured, the floors rise one slab at a time, and then the building is closed in and fitted out. Each stage depends on the one before it, and the work is checked as it goes.

The dates below come from a’Maré, our three full floor residences at 2 Bando Road in Cronulla, where we were the developer and the builder.

Securing the ground

A basement on a sandy coastal site cannot be dug with open sides, because sand will not hold a vertical face. The ground support goes in first. At a’Maré, a CFA piling rig was on site in January 2025 to build contiguous pile shoring, a wall of concrete piles set side by side around the perimeter of the one level basement. Our note on building near the water in the Sutherland Shire explains why sand changes the approach.

A capping beam ties the tops of the piles together. At a’Maré it was formed and poured along the pile wall between 16/02/2025 and 24/02/2025.

The crane

A crane needs a foundation of its own. Screw piles went in under the crane base on 06/02/2025, and the crane was installed in March 2025. From then on it lifted the materials for each floor above.

The basement

With the pile wall and capping beam holding the ground, the basement could be dug out. By early April 2025 the dig was almost complete, and the basement slab was poured on 14/05/2025.

The structure

Above the basement the building rises one floor at a time. Each level follows the same cycle: formwork to shape the slab, steel reinforcement laid inside it, then the concrete pour. At a’Maré, Level 2 was poured in October 2025, and the Level 4 pour was complete on 11/11/2025.

Below ground took about four months at a’Maré, from the piling rig in January 2025 to the basement slab in May. The frame then climbed through the rest of 2025, and by March 2026 the main structure was complete and ready for tiling and sheeting.

The structure is the stage that sets everything after it. A slab poured out of level or out of position shows up in every tile, door and window that follows, so it is checked before each pour.

Closing in

Once the frame is up, the building is closed in against the weather, and the facade begins to take shape. In March 2026, the external columns at a’Maré were clad over a membrane, glue, grout and sealer chosen to work together as one system. By May 2026 the automatic sun louvres were installed, and the plasterboard, tiles and stone were in.

Then the scaffold came down. In May 2026 the facade at a’Maré was fully revealed, more than a year after the piling rig arrived.

Fit-out

Inside, the services go in before the walls are closed. Plumbing, electrical cabling, air conditioning and data all have to be in place and checked while they can still be reached. Then come the joinery, the kitchens, the appliances and the finishes, and last of all the clean.

Before anyone moves in, an occupation certificate must be issued for the building. For a buyer, the last step is the inspection before settlement, and our note on what to check at a pre-settlement inspection walks through it.

Why the order matters to a buyer

If you buy off the plan, these stages are your progress markers. A basement pour, a slab on the top floor or the scaffold coming down each tells you where the building sits in the sequence. It is fair to ask the developer for photos of each stage and for the dates of the major pours. On our projects the developer and the builder are the same company, so those records sit in one place.

The sequence also explains why some changes are easy early and hard later. Moving a wall or a basin is a small change on the drawings, and an expensive one once the pipes and cables are in. Our note on what a construction manager does covers who keeps all of this in order on site.