A cost plus building contract means you repay the builder for the verified costs of the job, plus the builder’s fee, and there is no guaranteed final price. NSW guidance says it is often used where the nature of the project prevents the final cost from being worked out at the start. It suits some jobs very well and others not at all, so it pays to understand it before you sign one.

How a cost plus contract works

The builder buys the materials and pays the trades, then bills you for those costs along with the agreed fee at regular intervals. The NSW Consumer Building Guide describes these as verified direct and indirect costs and fees. Verified is the important word. You should see the invoices behind each claim and how that claim tracks against the budget, and if you cannot see both, ask the builder to change the report before the next one is due.

With a fixed price contract, the builder agrees to a set amount for the whole job at the start. That gives you a clear number, though the NSW guide notes that unforeseen changes during construction can still affect the final cost. The builder prices the risk in up front.

Under cost plus, that risk stays with you. So does the visibility, because you see where every dollar goes and you can make decisions as the work moves, which is a real advantage on a job where the design is still being settled on site.

When cost plus suits a job

It suits work where nobody can honestly price the whole job on day one. That usually means one of a few situations:

  • A one-off house on a difficult site, such as a block on the water where the ground holds surprises.
  • A design with materials and details that are still being resolved while the building goes up.
  • Work to an existing building, where you do not know what is behind the walls until they come off.

It suits an owner with the time to read reports. It suits a repeatable design far less, since a builder can price that with confidence and you would be carrying a risk for no reason.

What NSW requires in the contract

For work over $20,000, the NSW guide lists a number of things that must be in a home building contract. It must be in writing and must include the contract price or a warning that the price is unknown. It must also have a progress payment schedule and the details of the statutory warranties. Variations have to be in writing and signed by both parties. The maximum deposit you can be asked to pay before work starts is 10%.

The guide also sets out good practice for cost plus work. The builder should give you a non-binding estimate before starting, then track costs with you against the budgeted estimate. Read that word “non-binding” carefully, because an estimate under a cost plus contract is not a cap.

What to agree before you sign

Settle these points first. Your solicitor should read the contract with you, because this article is general information and does not replace legal advice.

The fee. Agree how it is worked out and what it covers. Site supervision and office costs can sit inside the fee or outside it, and you want to know which.

The reports. Ask for a report on a set day each month, showing actual costs against the estimate and the cost still to come. Agree on the format early.

The evidence. Every progress claim should come with its invoices and receipts. Ask how you will see them.

The decisions. Agree who can approve spending and up to what amount. Blowouts often start with small approvals nobody added up, so keep a running list.

The builder behind the contract

You carry the cost, so you rely on the builder’s honesty and on the people running the site. Before you sign, look at the work they have finished, ask who will run your site day to day, and ask to speak with someone who has been through this kind of contract with them.

How we use cost plus

We develop and build our own residences, and that is most of what we do. We take on construction work for other people only by choice, and only under a cost plus contract, when the job is the right one for us.

You can read more about how we work on our About page, or look through our record on the projects page. If you own land and want to develop it, a joint venture is another path worth reading about.