A development consent in NSW lasts for five years, unless the council sets a different period in the consent itself. Once physical commencement has occurred, the consent does not lapse, so the date that matters is the day work on the approved development properly starts on the land.

That gives a landowner or a developer a window, and on a development five years goes quickly. Inside it, the drawings, the certificates, the finance and the builder all have to come together.

The dates in a consent

NSW Planning calls a development consent a legal document that is extremely important, and the dates are the first thing to check in it. The period is five years unless the consent states another one. Check it in the consent itself, not from memory or a summary.

If the consent has since been modified, read the modified version together with the original. A modification can change the conditions and the approved plans, and the latest version is the one the work has to follow.

Keep the consent with the title documents for the site. Anyone who later buys the land, finances the project or builds it needs to see it.

What physical commencement means

Physical commencement means work on the land that belongs to the approved development. The test comes from the Environmental Planning and Assessment Act 1979 and its Regulation. If a consent is close to its lapse date and the plan is to keep it alive with a small amount of work, get advice from a planning lawyer first.

Before any of that work can start, the consent conditions have to be met. NSW Planning notes that some conditions are mandatory on every consent, and many consents list steps that must happen prior to the issue of a construction certificate. The construction certificate then has to be in place before building work begins. Our note on the DA, the CDC and the construction certificate sets out the order of those approvals.

What to check in a consent

  • The period. Five years unless the consent sets another.
  • The approved plans. The consent lists the drawings it approves, and the building has to match them.
  • The conditions. Some are standard on every consent, and others are written for the site. Note which ones must be met before a construction certificate can issue.
  • The fees and contributions. Any council contributions in the conditions belong in the project budget from the start.

Changes to an approved design

Designs change after approval. A consent can change with them. An application to modify a consent goes in under section 4.55 of the Environmental Planning and Assessment Act 1979. NSW Planning’s guide is clear that the development has to remain substantially the same as the one approved.

A change too large for that test needs a new development application. That is worth knowing early, because a new application starts the assessment again.

If the decision goes against you

An applicant who disagrees with a decision has two paths, and both have deadlines. The first is a review of determination by the council, with amended plans if the applicant wants, and NSW Planning’s guide says that request has to be lodged and determined within six months of the decision. The second is an appeal, and the same guide gives six months to lodge it.

Which path suits a site is a legal question. A planning lawyer is the right person to ask, and the clock starts on the date of the decision.

Why the lapse date matters to a landowner

A consent is part of what a landowner brings to a buyer or a development partner. A consent close to its lapse date leaves either of them only a short window to finance the project and start work. Our note on how a development joint venture works covers what each side brings to that kind of arrangement.

On a development we take from approval into construction, the lapse date sits at the top of the programme. The construction certificate, the finance and the trades all need to be lined up well before the window closes, and starting on site is the step that secures the consent. If you hold a consent and want to know what it would take to start, talk to us.