A planning proposal is a request to change a Local Environmental Plan, the legal document that sets what can be built on each block of land in a council area. Landowners use one when the zoning or the development standards on a site stand in the way of a project the site could carry.

What the plan controls

Each Local Environmental Plan sets the zoning of land in its area and the uses permitted or prohibited in each zone. It also sets development standards such as building height, floor space ratio and minimum lot size. Floor space ratio compares the floor area of a building with the area of its site. A ratio of 1:1 on a 1,000 square metre block allows 1,000 square metres of floor area. The height limit and the other controls decide how many floors that area can spread across.

In the Shire, the plan is the Sutherland Shire Local Environmental Plan 2015.

When you need one

Not every gap between the rules and a project needs a new plan. Where a full amendment is not required, a development application can ask to vary a development standard under clause 4.6. A planning proposal is for changes the plan itself has to make. That means a new zone, a new permitted use, or a different height or floor space ratio across the site. When the rezoning and the project go together, the planning proposal and the development application can be prepared and assessed at the same time.

Check what State policy already allows before you start. Near nominated stations and town centres, the Low and Mid-Rise Housing Policy now permits some housing types in zones where local plans did not.

The five stages

The NSW Government sets out five stages:

  1. Scoping. This comes before formal lodgement, and the Government recommends it for complex proposals. The proponent prepares a scoping report on the proposal, the site, its preliminary strategic merit, its key issues and the studies it is likely to need. After a meeting, council gives written advice on the category, standard or complex, the studies required and a first view on merit.
  2. Planning proposal. The proposal sets out its objectives and the changes it seeks to zoning, land use or standards. It adds the justification, existing and proposed maps, the consultation approach and a timeline. It is lodged through the NSW Planning Portal. Council assesses it, takes advice from the Local Planning Panel where required, and decides whether to support it and send it on to Gateway.
  3. Gateway determination. The NSW Government decides whether the proposal should proceed.
  4. Post gateway and public exhibition. The proposal goes on public exhibition, so the community can see it and comment.
  5. Finalisation. The change to the plan is made.

If council will not support a proposal, the proponent can ask the Department of Planning, Housing and Infrastructure for a review. The Department also publishes benchmark timeframes for each category of proposal.

What makes a proposal succeed

A proposal has to describe the change, justify it, and show both strategic merit and site-specific merit. Both tests have to pass. Strategic merit asks whether the change fits the regional and local plans for the area, including the council’s local strategic planning statement. It also asks whether the area needs the growth, housing or jobs the change would bring. Site-specific merit asks whether this land suits the use, whether its effects on the environment are understood and can be managed, and whether the utilities, transport and other services can support it.

That is why the work starts with evidence. Flooding, bushfire, contamination and biodiversity all end up in the studies, and the studies are what council and the Department read. A thin proposal tends to come back with requests for more information, and every request adds time.

Joint ventures and planning proposals

A planning proposal takes time, studies and money before a single home is built, and the landowner carries that cost whether or not the change is made. For a landowner who wants the result without carrying that alone, a development joint venture is one way through: you bring the land, and we bring the finance and the delivery. Planning proposals sit within our planning work, alongside feasibility studies and development applications.

The first step either way is to learn what the current rules allow, and that is what a feasibility study does.